Fibre projects: implementation & relocation
Project Description Project Duration Route Distance Remark
Glo Mobile Benin-Agbor Project (Material supply, shipping, warehousing, insurance, civil & cable works)
4 Weeks
13km
100% Completed
Glo Mobile Benin-Agbor Project (Material supply, shipping, warehousing, insurance, civil & cable works)
40 Weeks
65km
100% Completed
Glo Mobile Relocation of Owerri-Asaba fibre infrastructure (Civil & Cable works)
4 Weeks
5km
100% Completed
Glo Mobile Relocation of Aba-PHC fibre infrastructure (Civil & Cable works)
6 Weeks
8km
100% completed
IPNX Fiber optic cabling of Cooper road ( Civil & cable works)
4 weeks
5km
100% completed
IPNX fibre connection to GLO 1 Port Harcourt ( Civil & cable works)
1 week
2km
100% completed
IPNX Fibre optic project of Parkview Estate Lot 1, 2, 3 & 1B ( Civil & cable works)
5 months
20km
100% completed
CVComms/MTN outdoor DAS projects at Onitsha, Enugu, Ariaria & Wuse markets (Civil & cable works and Support)
5 weeks
5km
Implementation completed, Support on-going